Read an Excerpt
Chapter 1
Why Project Risk Management?
Far too many technical projects retrace the shortcomings and
errors of earlier work. Projects that successfully avoid such pitfalls are often
viewed as “lucky,” but there is usually more to it than that.
The Doomed Project
All projects involve risk. There is always at least some level of uncertainty
in a project’s outcome, regardless of what the Microsoft Project
Gantt chart on the wall seems to imply. High-tech projects are particularly
risky, for a number of reasons. First, technical projects are highly varied.
These projects have unique aspects and objectives that significantly differ
from previous work, and the environment for technical projects evolves
quickly. There can be much more difference from one project to the next
than in other types of projects. In addition, technical projects are frequently
“lean,” challenged to work with inadequate funding, staff, and
equipment. To make matters worse, there is a pervasive expectation that
however fast the last project may have been, the next one should be even
quicker. The number and severity of risks on these technical projects
continues to grow. To avoid a project doomed to failure, you must consistently
use the best practices available.
Good project practices come from experience. Experience, unfortunately,
generally comes from unsuccessful practices and poor project
management. We tend to learn what not to do, all too often, by doing
it and then suffering the consequences. Experience can be an invaluable
resource, even when it is not your own. The foundation of this book is the
experiences of others—a large collection of mostly plausible ideas that
did not work out as hoped.
Projects that succeed generally do so because their leaders do
two things well. First, leaders recognize that much of the work on any project,
even a high-tech project, is not new. For this work, the notes, records,
and lessons learned on earlier projects can be a road map for identifying,
and in many cases avoiding, many potential problems. Second, they plan
project work thoroughly, especially the portions that require innovation,
to understand the challenges ahead and to anticipate many of the risks.
Effective project risk management relies on both of these ideas.
By looking backward, past failures may be avoided, and by looking
forward through project planning, many future problems can be minimized
or eliminated.
Risk
In projects, a risk can be almost any uncertain event associated
with the work. There are many ways to characterize risk. One of the simplest,
from the insurance industry, is:
“Loss” multiplied by “Likelihood”
Risk is the product of these two factors: the expected consequences
of the event and the probability that the event might occur. All
risks have these two related, but distinctly different, components. Employing
this concept, risk may be characterized in aggregate for a large
population of events (“macro-risk”), or it may be considered on an eventby-
event basis (“micro-risk”).
Both characterizations are useful for risk management, but which
of these is most applicable differs depending on the situation. In most
fields, risk is primarily managed in the aggregate, in the “macro” sense. As
examples, insurance companies sell a large number of policies, commercial
banks make many loans, gambling casinos and lotteries attract
crowds of players, and managers of mutual funds hold large portfolios of
investments. The literature of risk management for these fields (which is
extensive) tends to focus on large-scale risk management, with secondary
treatment for managing single-event risks.
To take a simple example, consider throwing two fair, six-sided
dice. In advance, the outcome of the event is unknown, but through analysis,
experimenting, or guessing, you can develop some expectations. The
only possible outcomes for the sum of the faces of the two dice are the integers
between two and twelve. One way to establish expectations is to
figure out the number of possible ways there are to reach each of these
totals. (For example, the total 4 can occur three ways from two dice: 1 +
3, 2 + 2, and 3 + 1.) Arranging this analysis in a histogram results in Figure
1-1. Because each of the 36 possible combinations is equally likely, this
histogram can be used to predict the relative probability for each possible
total. Using this model, you can predict the average sum over many
tosses to be seven.
Figure 1-1. Histogram of sums from two dice.
If you throw many dice, the empirical data collected (which is another
method for establishing the probabilities) will generally resemble
the theoretical histogram, but because the events are random it is extraordinarily
unlikely that your experiments rolling dice will ever precisely
match the theory. What will emerge, though, is that the average
sum generated in large populations (one hundred or more throws) will be
close to the calculated average of seven, and the shape of the histogram
will also resemble the predicted theoretical distribution. Risk analysis in
the macro sense takes notice of the population mean of seven, and casino
games of chance played with dice are designed by “the house” to exploit
this fact. On the other hand, risk in the micro sense, noting the range of
possible outcomes, dominates the analysis for the casino visitors, who
may play such games only once; the risk associated with a single event—
their next throw of the dice—is what matters to them.
For projects, risk management in the large sense is useful to the
organization, where many projects are undertaken. But from the perspective
of the leader of a single project, there is only the one project.
Risk management for the enterprise, or for a portfolio of projects, is
mostly about risk in the aggregate (a topic explored in Chapter 13). Project
risk management focuses primarily on risk in the small sense, and
this is the dominant topic of this book.
Macro-Risk Management
In the literature of the insurance and finance industries, risk is described
and managed using statistical tools: data collection, sampling, and
data analysis. In these fields, a large population of individual examples is
collected and aggregated, and statistics for the “loss and likelihood” can be
calculated. Even though the individual cases in the population may vary
widely, the average “loss times likelihood” tends to be fairly predictable
and stable over time. When large numbers of data points from the population
at various levels of loss have been collected, the population can be
characterized using distributions and histograms, similar to the plot in Figure
1-2. In this case, each “loss” result that falls into a defined range is
counted, and the number of observations in each range is plotted against
the ranges to show a histogram of the overall results.
Figure 1-2. Histogram of population data.
Various statistics and methods are used to study such populations,
but the population mean is the main measure for risk in such a population.
The mean represents the typical loss—the total of all the losses
divided by the number of data points. The uncertainty, or the amount of
spread for the data on each side of the mean, also matters, but the mean
sufficiently characterizes the population for most decisions.
In fields such as these, risk is mostly managed in the macro sense,
using a large population to forecast the mean. This information may be
used to set interest rates for loans, premiums for insurance policies, and
expectations for stock portfolios. Because there are many loans, investments,
and insurance policies, the overall expectations depend on the average
result. It does not matter so much how large or small the extremes
are; as long as the average results remain consistent with the business objectives,
risk is managed by allowing the high and low values to balance
each other, providing a stable and predictable overall result.
Project risk management in this macro sense is common at the
project portfolio and enterprise levels. If all the projects undertaken are
considered together, performance primarily depends on the results of
the “average” project. Some projects will fail and others may achieve
spectacular results, but the aggregate performance is what matters to
the business bottom line.